Major Activities:
A) Baseline Survey
B) Exposure Visit
C) Skill Development Training of 250 Rural Youth
D) Stake-Holder Consultation Meeting
E) Common Infrastructure Development
Till date Agragamee, the implementing agency has been
conducted the following key activities under the ERYA (Encouraging Rural Youths
in Agriculture) project in Nabarangpur District of Odisha.
- The Baseline Survey for
selection of 250 rural youth has completed to shortlist 750 Rural Youth
of ERYA Project.
- The indicative list of 375 youth
for first set of 125 youth for first year (2024-25) has been completed.
- Agragamee has been consulted
with the all relevant line departments like Agriculture, Horticulture,
Fisheries, Animal Husbandry, Krishi Vigyan Kendra (KVK), Umerkote and
CBO/FPOs to select final youth for ERYA project.
- 2 nos. of Skill Development
Training on “Commercial Mushroom Cultivation” have completed for 50
youth trainees.
- One Skill Development Training
on “Fishery and Poultry Farming” has been conducted for 25 youth
trainees.
- 2 nos. Exposure Visit of 50
youth trainees under “Commercial Mushroom Cultivation” training have
completed.
- One Exposure Visit of 25 youth
trainees under “Fishery and Poultry Farming” training have completed.
- Till date 50 trained youth have
started Mushroom Cultivation as post training activities. Total 47.06
Qtl. of Oyster Mushroom has been harvested by 50 youth out of which 41.3
Qtl. of Mushroom has been sold by 50 youth in local market @18000/- per
Qtl. Total Rs. 7.43 Lakh has been generated as income from Oyster
Mushroom by 50 youth.
- The Model Business Plan of 5
Agri Trades (Commercial Mushroom Cultivation, Nursery Raising and
Management, Fishery, Certified Seed Production & Organic Input
Production) has prepared by Agragamee.
- Till date 7 nos. of Project
Monitoring and Review Committee (PMRC) meetings have conducted (1st
Meeting – dt. 7.11.2023, 2nd Meeting – 31.01.2024, 3rd Meeting –
20.06.2024, 4th Meeting – 9.08.2024, 5th Meeting – 27.09.2024, 6th
Meeting – 19.12.2024 and 7th Meeting – 17.01.2025). The proceedings of
all these PMRC meetings have submitted to the RO accordingly.
- All the above project
activities have been conducted as per action plan and suggestion of the
PMRC members.
- The training module of 7
agriculture activities has completed with the help of line departments
and the PMRC members.
- The PMRC members visited the
sites of three Mushroom Production and Spawn Units established by the
youth of 1st batch trainee of Commercial Mushroom Cultivation in
Nandahandi and Nabarangpur Blocks in Nabarangpur on dt. 17.01.2025.